[Construction Example] Miyagi Prefecture Port Facility Quay Disaster Recovery Work
Harbor facility quay disaster recovery work
In 2021, the earthquake off the coast of Fukushima caused multiple ground fissures in the loading area and storage yard of the Hibari district in Ishinomaki and Shiogama ports. Traditionally, repairs for similar ground fissures involved open excavation down to the deepest part of the fissure, followed by repeated compaction to create a subgrade. However, this time there were several challenges, leading to the decision to explore methods that could fill the fissures without excavation and within a short construction period. Among these, the Upcon method was adopted as the most effective technique. 【Site Information】 Total construction length: 503 m Maximum depth of fissure: 2,400 mm Construction period: 5 days For detailed explanations and observations of the construction, please refer to the PDF download below.